Hello
As you can see below, the time increment in my NLG plastic
Consolidation analysis (Transient Soil Step) drops dramatically and
suddenly by almost 5 orders. Is that material failure? . What can i
doif my analysis time span is in the order of 1E+08, while the time
increment after that moments seems to continue with order of 1.
This means that I need several days to complete a single analysis, if
the job doesnot abort. Please advise
3 7.94706e+07 1.94706e+07 4696.5
8 7.9471e+07 1.9471e+07 440.297
7 7.94711e+07 1.94711e+07 110.074
3 7.94711e+07 1.94711e+07 27.5186
4 7.94712e+07 1.94712e+07 27.5186
1 7.94712e+07 1.94712e+07 0.644967
1 7.94712e+07 1.94712e+07 1.28993
3 7.94712e+07 1.94712e+07 2.57987
2 7.94712e+07 1.94712e+07 0.96745
Thank you